Horley Bowling Club
Extraordinary General Meeting
Tuesday 21 July 2026 – 6.00 pm
Site Improvement Project – Phase 1 Proposal
Purpose of this Paper
The purpose of this paper is to provide members with the background to the proposed Phase 1 Site Improvement Project and to seek members’ approval, in accordance with the Club Constitution, to proceed with the proposed expenditure and delivery of the first phase of works.
Under the Constitution, members must approve expenditure exceeding the agreed financial limit of £7500. In addition, the Committee wishes to ensure that members have the opportunity to consider how the Club should use the external funding that has been secured.
Background
Over the past two years building on members ideas for improvement the Committee has been developing a long-term improvement plan for Horley Bowling Club.
The aims of the project are to:
The overall project has always been planned as a series of stages rather than one large scheme.
Stage 1
Improve accessibility, safety, pathways, storage and the spectator/social area.
Stage 2
Reconfigure and improve the internal clubhouse spaceto provide folding doors to the green, a larger space for short mat, improved bar and catering facility and small lounge for socialising and after match refreshment .
Stage 3
Potential future extension of the clubhouse, to provide a youth room better entry to club hose and improved club access for wheelchairs and those with poor mobility issues. This stage will be subject to funding and Horley Town Council approvals.
Project Development and Approvals
The Site Improvement Project has been developed over the past two years following discussions with members and consideration by the Committee and the Site Improvement Working Group. The original concept was to improve accessibility, safety, storage and spectator facilities around the green while creating the circumstances for the club infrastructure to be reconfigured through a phased programme of improvements that could be delivered as external funding became available.
The first formal funding application was submitted to the Reigate & Banstead Community Infrastructure Levy (CIL) Fund in 2025. Although that application was ultimately unsuccessful, it enabled the Club to develop detailed plans, cost estimates and a phased delivery programme. The proposals were subsequently refinedto meet the criteria for other funding sources and presented to Horley Town Council’s Leisure Committee, which gave its support in principle. Following further discussion and amendments, the project was then presented to the full Horley Town Council, which approved the Stage 1 proposals and granted the necessary landlord consent for the Club to proceed with external funding applications.
These approvals enabled the Club to submit successful applications to Sport England and, more recently, the Surrey Community Foundation, securing a total of £21,500 of external investment for accessibility and site improvements. The proposals before members is therefore the culmination of an extensive period of planning, consultation and external approval rather than a new proposal.
Funding Success
Although less funding than originally requested from the Reigate and Banstead Community Levy fund the Club has been successful in securing other external funding.
Sport England has awarded the Club £15,000 to improve:
In addition, the Club has recently secured a further £6,500 from the Surrey Community Foundation to purchase specialist accessibility equipment including:
Together these grants represent an external investment of £21,500 into Horley Bowling Club, which allows us to relook and re–phase the project.
Why are we re–phasing the project?
When the original funding applications were preparedfor Phase 1, cost estimates were based on prices obtained more than a year ago.
Following confirmation of the Sport England grant, the Improvement Working Group developed a detailed tender specification and invited contractors to submit competitive quotations. The specification was deliberately prepared so that individual elements of the work could be priced separately, allowing the Club to deliver the project in phases if the available funding proved insufficient.
Four competitive tenders were received. As anticipated, the cost of delivering the full Phase 1 project exceeded the £15,000 Sport England grant, although two contractors prices would be within the money available if the scope was reduced..
The increase in costs reflects a number of factors:
The Committee therefore reviewed the tenders and considered how the Club could still deliver the key objectives agreed with Sport England while remaining within the available funding. This has led to the development of the phased options set out in this paper.
Recommended Approach
Rather than abandon the project or return the grant, the Working Group recommends delivering the improvements in phases.
This approach allows the Club to:
The Committee believes this is the most sensible and financially responsible approach.
The Options Considered
After reviewing the tenders, the Committeedeveloped three possible approaches.
Option A
Improved accessibility and creation of a player,spectator/social space
This proposal focuses on delivering the greatest immediate benefit in terms of safety, accessibility and circulation around the green. The works would:–
Advantages
Disadvantages
Option B
This proposal retains more of the existing layout while beginning the longer-term redevelopment programme.The works would:
Advantages
Disadvantages
Option C
Return the Sport England Grant and Use Club Reserves to Undertake Essential Repairs Only
This proposal would not proceed with the wider Phase 1 improvement project. Instead, the Club would return the Sport England grant and use its own reserves to carry out essential maintenance works to improve the safety of the existing pathways. The works would include:
Advantages
Disadvantages
Committee Recommendation
After considering these options, the majority of theCommittee believe that Option B provides the greatest overall benefit but wish to find out what members prefer.
The rationale for recommending option B is it:
Funding Later Phases
The Committee recognises that Phase 1 options being considered will not complete the overall improvement programme.
Future phases will continue to be funded through further bids to :
No commitment is being sought at this meeting for later phases.
What Members Are Being Asked to Approve
Members are asked to approve:
Looking Ahead
This project represents the largest external investment in Horley Bowling Club in the last 28 years.
It will:
The Committee therefore recommends that members support the proposed Phase 1 Option B improvements.
Annexes
Annex A
|
|
Option A: |
Indicative price needs to be confirmed with preferred contractor |
|
Item |
Description of Work |
Price Inc VAT (£) |
|
1 |
Site set-up, protection of green and surrounding areas |
960 |
|
2 |
Making good existing paving (cleaning, some lifting, re-bedding, re-levelling slabs. Replacement of damaged slabs. Dimensions 40 metres by 1.7 metres x 4. |
4,600 |
|
3 |
Removal of flower bed including excavation and removal of contents |
2,200 |
|
4 |
Ground preparation for new paving area. Purchasing and laying extended patio on the playground side –11 metres by 2 metres (22 square metre patio) |
4400 |
|
6 |
Remove playing equipment shed base construct a newbase for playing equipment shed |
1130 |
|
7 |
Dismantle and rebuild playing equipment storage in new location |
450 |
|
8 |
Remove and relocate one shelter |
750 |
|
9 |
Site clearance and waste removal including skip hire |
800 |
|
10 |
Final cleaning and making good |
650 |
|
|
Total with vat |
15,940 |
|
|
Option B |
Indicative price needs to be confirmed with preferred contractor |
|
Item |
Description of Work |
Price Inc VAT (£) |
|
1 |
Site set-up, protection of green and surrounding areas |
960 |
|
2 |
Making good existing paving (cleaning, some lifting, re-bedding, re-levelling slabs. Replacement of damaged slabs. Dimensions 40 metres by 1.7 metres x 4.
|
4600 |
|
3 |
Removing large brown storage shed |
450 |
|
4 |
Construction of base for replacement maintenance storage shed |
2400 |
|
5 |
*Supply of new maintenance storage sheds either custom made from existing materials £3,000 or ready -made contractor sourced shed for £1700 or resilient metal shed £6000 * |
3000* |
|
6 |
Erection and installation of new maintenance storage shed |
1595 |
|
7 |
Ground preparation for new paving area. Purchasing and laying extended patio on the playground side – 6 metres by 2.metres (12 square metre patio) |
2400 |
|
11 |
Site clearance and waste removal including skip hire |
800 |
|
12 |
Final cleaning and making good |
650 |
|
13 |
Planning permission application |
500 |
|
|
Total with Vat With metal shed |
17,355 20,355 |